Why would the City of San Diego spend $4.29 million raising fishing piers at a lake that, from the loop path, looks the way it always has? Because the lake won't stay this way. The City expects Miramar Reservoir to rise about four feet. The rise should start gradually in early 2027 and keep climbing for roughly six to 12 months after that.
The docks and walkways are being rebuilt first so they're ready for that new waterline. The City lists the Miramar Reservoir Recreation Facilities project as started in Fall 2026. That means the East, West and Natalie fishing piers, the floating docks and the timber walkway are all scheduled for work over the coming months. Lake Miramar is taking on a new role in the city's water system, and the shoreline is being set up for it.
Where the extra four feet comes from
Miramar Reservoir has been picked as the storage point for advanced purified water from the North City Pure Water Facility. That facility is the centerpiece of Phase 1 of Pure Water San Diego. Phase 1 is designed to deliver 30 million gallons a day to the reservoir. That water is stored there and then treated again at the Miramar Drinking Water Treatment Plant before it reaches anyone's tap.
Much of the route runs through Scripps Ranch. According to the City's Scripps Ranch and Miramar project page, the North City Pure Water Pipeline starts at Eastgate Mall and follows Miramar Road. It then tunnels under Interstate 15 and continues along Business Park Avenue, Carroll Canyon Road, Hoyt Park Drive and Meanley Drive, then crosses Scripps Lake Drive to the reservoir. A Dechlorination Facility across Scripps Lake Drive, at the southwest corner of the reservoir, removes the chlorine used to protect the pipe before the purified water is blended into the lake. On the lake floor, a one-mile branched subaqueous pipeline spreads the incoming water evenly. Crews built it on barges at the surface and then sank it into place.
Many regulars will remember that barge work. Less of the pipeline is visible from the trail today, but it isn't finished. The City's January 2026 annual report put the pipeline, dechlorination and subaqueous project at 79% complete as of Fall 2025. By then more than 36,000 linear feet of pipe were in the ground, and hydrostatic testing was expected to continue through 2026. The same report says new landscaping was going in at the reservoir in December 2025. It replaced plantings removed for the subaqueous pipeline and parking lot work, and it screens the neighboring Miramar Drinking Water Plant.
The water itself comes later than some City pages suggest. As of this October, the project page still lists 2026 for completion of the North City facility. The more recent schedule, reported by the San Diego Union-Tribune in January 2026, has Pure Water San Diego producing purified water in early 2027 and ramping up to 30 million gallons a day by the end of 2027. The same article puts that output at nearly 20% of San Diego's water.
That's a big job for the lake at the end of Scripps Lake Drive. The Miramar Water Treatment Plant beside it has a capacity of 144 million gallons a day and serves about 500,000 customers, mostly in the northern part of the city.
Why the piers have to move before the water does
A pier set for today's waterline won't work once the lake is four feet higher. The aluminum brows linking land to the floating docks would sit at different angles, and the timber walkway's lowest section would end up too close to the water. The May 2026 project fact sheet says the work covers ADA accessibility and the higher water level. It lists these changes:
- Extending the columns under the East, West and Natalie fishing piers so their docks sit higher.
- Removing the aluminum brows that connect the floating docks and piers to land, and replacing the floating fishing piers and docks.
- Retrofitting parts of the accessible boat dock and the courtesy docks.
- Extending columns to raise the timber walkway that leads to the accessible boat dock, and removing the stretch of walkway closest to the water.
- Improving the concrete walkways next to the timber walkway and adding paved walkways and a concrete sidewalk from the main parking lot to the docks.
- Building an ADA-accessible path, a guardrail system and an accessible parking area at the West fishing pier.
- Adding bollards to the East fishing pier parking area.
- Installing signage and restriping within the East and West fishing piers.
Most of these changes either lift something up or take out a low section. The fishing spots locals know by name will stay where they are, just higher. The walkway section that's being removed is the part a four-foot rise would reach first.
How the next year is scheduled to unfold
The City's own documents give slightly different end dates, so the table shows both.
| Period | What the City has scheduled | Source |
|---|---|---|
| Fall 2026 | Recreation facilities work begins | City project page |
| Fall 2026 to Summer 2027 | Construction window | May 2026 fact sheet |
| Early 2027 | Pure Water production begins; reservoir starts rising incrementally | Union-Tribune, City project page |
| About 6 to 12 months after the rise starts | Gradual climb toward the full rise of about four feet | City project page |
| End of 2027 | Pure Water reaches 30 million gallons a day | Union-Tribune |
| Fall 2027 | Recreation project completion | City project page |
The overlap matters. If both schedules hold, crews should have most of the docks and piers raised before the reservoir has risen much. The City notes that both the schedule and the budget may change. Construction notices are listed on the project page as coming soon, so the start dates for individual pier closures haven't been posted yet.
What changes on a weekday visit
Work is scheduled Monday through Friday from 8:30 a.m. to 3:30 p.m. If you usually visit before work or in the late afternoon, you'll mostly miss the crews. Weekday mornings are a different story. Construction vehicles and materials will use the main parking lot, so the lot you're used to may have fewer open spaces.
Fishing and the access road stay open throughout the project. The boat ramp will close temporarily when crews are working right at the ramp or pulling the floating fishing piers out of the water there. Docks, piers and walkways will also have interruptions as each one is retrofitted. The City says it will announce these closures in advance. Notices will be distributed to properties around the reservoir, posted online, and stocked in the kiosk literature boxes in each parking lot. If you launch a kayak or fish from a pier, check those kiosks before you unload.
Some things on the lake haven't changed. The City's Miramar Reservoir page still lists the same rules:
- Open daily, sunrise to sunset, except the first Tuesday of each month.
- Closed on Thanksgiving, Christmas and New Year's Day, so plan holiday-week walks around Thursday, November 26.
- Boats, canoes, kayaks and float tubes are allowed, along with fishing.
- An algae advisory is posted with no issue date. The City asks visitors to avoid touching the water and to keep pets from entering or drinking it, and it says the bloom doesn't affect treated drinking water. Check the page before you bring a dog.
For pier-by-pier questions, the project team's line is 833-MIR-PWSD, or 833-882-7973. The fact sheet says calls are returned within one business day, and you can join the email list for notices at [email protected].
Neighborhood projects like this, from new piers to a higher lake to a new role in the city's water supply, tend to come up when people talk about Scripps Ranch homes near the water. If you'd like a calm, informed conversation about how changes around Lake Miramar fit into your own plans, Lani Bautista is glad to help. Schedule a Consultation.